The floor was done when I arrived
|
Plywood on 4x4s, concrete blocks, and crushed stone
|
Sidewalls up
|
Were stickbuilt on the driveway and carried down
|
Then the front and back walls
|
Framing nailer made things easier
|
Then the plywood siding (end of day 1)
|
Rafters at the end to start the roof
|
Then the dual 2x6 ridgebeam (end of day 2)
|
Followed by rafters all the way across
|
And the end plywood (note overlap)
|
End almost finished and window cut out
|
Lookouts in the p.m.
|
Closer look at the lookouts
|
Facia on the front and sides
|
Full frontal view
|
One row of plywood
|
End of day 3
|
Tarpaper over the plywood
|
Shingles over the tarpaper
|
End of day 4 (careful up there!)
|